show date: APRIL 30, MAY 1
|
FEBRUARY
|
february 1-6
|
Production:
-
Story boarding (preliminary)
-
Develop overall story board
-
Develop individual scene shots
-
Modeling
-
create main character
-
environment
-
look at early german expressionist films
-
check out bladerunner for sets
Figure out location for Show: tentatively BSB 250
|
february 7-13
|
Production:
-
Modeling
-
secondary characters
-
environment
-
Lighting
-
first scene, aerial shots
-
Texture Mapping
-
first scene, aerial shots
-
Animating
-
camera movements of first scene
-
test renders for environment depth and lighting effects
Get old claymation put to tape (Hamlet...).
Acquire sources for advertisement.
Begin work on invitations
|
february 14-20
|
Production:
-
Modeling
-
secondary characters
-
environment
-
Lighting
-
develop lighting continuities
-
Texture Mapping
-
Animating
-
walk, and expressions for characters
-
develop overall timing- sketch out each scene.
-
produce test renders
-
work on timing
|
february 21-28
|
Production:
-
Modeling
-
secondary characters
-
environment
-
Lighting
-
Texture Mapping
-
Animating
-
work on next couple of scene shots
-
output test renders to video tape.
-
work on timing
|
MARCH
|
march 1-6
|
Due date for Tom Frisch on verbal commitment, whether he will
have his stuff done by show time.
Production:
|
march 7-13
|
Production:
-
Animating
-
Rendering
-
Create flyers for advertising
|
march 14-20
|
Production:
-
Animating
-
Rendering
-
Print out invitations
|
march 21-27
|
Production:
Advertising:
|
march 28-31
|
Production:
-
Rendering
-
Acquire background sound.
|
APRIL
|
april 1-3
|
Production:
-
Rendering
-
Learn MAYA
-
Edit first cut
Advertising:
-
Send out information to publications
|
april 4-10
|
Production:
-
Rendering
-
Editing
-
Learn MAYA
-
Send first edit to Sean O'Loughlin for music
|
april 11-17
|
Production:
|
april 18-22
|
Production:
|
april 23-29
|
Production:
-
Editing
-
Dumping to Tape
-
Show prep
|
april 30
|
S H O W T I M E ! ! !
|
MAY
|
may 1
|
S H O W T I M E ! ! !
|